Construction management: construction
During this stage the construction manager takes possession of the site and carries out the construction works. As each trade contract is completed, individual certificates of practical completion must be issued, and then a certificate of project completion issued once all trade contracts are complete.
Contents |
[edit] Starting the work stage.
The construction manager arranges a handover meeting to take possession of the site. See article handover to contractor.
Before work on site proceeds, the client and the construction manager (in their role as as principal contractor) confirm that suitable welfare facilities have been provided and the construction manager (in their role as as principal contractor) confirms that a suitable construction phase plan has been prepared.
When appropriate, the construction manager issues notices for each trade contractor to commence work on site along with instructions regarding phasing and sequencing of the works. The construction manager should then keep trade contractors informed about the progress of the project so that they are able to plan their works in advance of receiving a notice to commence work.
[edit] Construction.
The construction manager manages, schedules, supervises, organises and co-ordinates the trade contractors and preliminaries packages on a day-to-day basis. The construction manager is generally the principal contractor under the CDM regulations as well as having overall responsibility for the site management, and is responsible for welfare provisions, site clearance, waste disposal, site security and trade union issues.
The lead designer co-ordinates the preparation of any additional information required by the trade contractors for construction.
The construction manager co-ordinates the issue of any additional information required by the trade contractors and co-ordinates the review of design information prepared by the trade contractors.
Where there are any proposed variations, procedures for their valuation should be implemented (as described in the contract). Where variations exceed the delegated authority of the construction manager, approval should be requested from the client.
The construction manager co-ordinates site inspections, issues instructions as required and assesses any claims for extension of time or loss and/or expense with advice where appropriate from the consultant team.
The construction manager issues regular payment notices to each trade contractor. The notices must be issued within five days of the dates for payment set out in the contract. If they intend that the trade contractors should be paid a different amount, they must issue a pay less notice giving the basis for the calculation of the amount that will be paid. The client must then make payments to the trade contractors by the final date for payment.
On large projects the construction manager may hold a daily logistic meeting on site with trade contractor foremen to organise, schedule and co-ordinate on-site shared services such as deliveries and offloading, hoists and craneage, scaffolding and safety issues, rubbish clearance etc.
The construction manager performs weekly checks on trade contractor earned value and takes action if necessary
The construction manager holds regular construction progress meetings with trade contractors (and on large projects, with the construction manager's package manager) to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractors premises.
The construction manager holds regular construction progress meetings with the client and consultant team and progress reports are prepared for the client.
[edit] Preparing for occupation.
The client begins preparations for occupation of the development, including the preparation of an operational policy and migration strategy (see links for detailed guidance) setting out how they will manage the transition into and the operation of the new facility.
The client may have an 'occupation services contract' for delivering and installing equipment, fixtures and furniture (sometimes from other premises). This contract may also pick up small building changes that they consider would be costly if instructed under the main contract.
The client should ensure they have sufficient funds to release 50% of the retention (where the contract provides for retention) upon certification of practical completion for each trade contract.
[edit] Inspections, commissioning and testing.
The construction manager agrees procedures for inspections, commissioning, testing and client training with the consultant team and client (representatives of the facilities management department).
If it has not already been done, the client appoints an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as project (or sectional) completion is certified.
The services engineer co-ordinates procedures for inspections, commissioning, testing and client training in relation to building services. The construction manager co-ordinates procedures for inspections, commissioning, testing and client training in relation to other aspects of the building.
The trade contractors rectify any defects that become apparent during commissioning, testing and inspection procedures.
[edit] Practical completion.
The construction manager prepares a draft building owner's manual and and if required a building user's guide and the lead designer co-ordinates the preparation of the building log book. The principal designer completes the health and safety file.
The trade contractors confirm to the construction manager that their works are complete.
The construction manager issues a certificate of practical completion and payment notice for each trade contract as it is completed. If they intend that the trade contractors should be paid a different amount, they must issue a pay less notice giving the basis for the calculation of the amount that will be paid. The client pays the amount due by the final date for payment (this may include the release of half of the retention if provided for in the contract).
The construction manager should take steps to protect completed work from any ongoing work.
Once all of the trade contracts are complete (or all of the trade contracts in a section of the works) the construction manager arranges for final inspection of the works by the building control inspector (or approved inspector) and arranges for the issue of a building regulations completion certificate. NB Within 5 days of the completion of the building, the construction manager must notify building control that the works have been carried out in accordance with the specification submitted with the building emission rate (BER) calculations, or the changes that have been made (see emission rates for more information).
Once all of the trade contracts are complete (or all of the trade contracts in a section of the works), the construction manager issues a certificate of project completion (or sectional completion).
The construction manager arranges a handover meeting to confirm that the works are complete and to handover the site to the client (see article handover to client).
The construction manager prepares and submits a construction stage report for the client. The client assesses the construction stage report, and gives instructions as necessary. ew
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.